Airport Cast in Place Structures

Lambert Cast in Place

Part of the Lambert International Airport Expansion contract included significant
cast in place structures:

  • 28,000 lf of Storm Sewers Ranging from 15” to 84” RCP
  • 86 Design-Build, Aircraft-Loaded Cast-In-Place Structures
  • Modification to Contract for 55’ Tall, Cast-In-Place Storm Structure
    • Work Was Reassigned from Other Contracts
  • 500’ 8 x 21 Cast-In-Place Box Culvert
  • 1,600 sy Paved Swale
  • Worked Within Airfield Operations Area (AOA) and Around Existing Airfield Maintenance Facility
  • Mitigated Drainage Problems Created by Other Contractor’s Performance
  • Sequencing Installation of New Utilities; Abandonment of Existing Utilities
PROJECT INFO
Client:
City of St. Louis, Missouri
KG’s Role:
General Contractor
Location:
Bridgeton, Missouri
Contract Value:
$8 Million